Dear Ionic Team
ReplyDeleteFirst of all thanks a lot for the reply.
We have noted the following points of your reply.
1. VVMC approval is expected shortly.
2. Registration process will start after immediately after VVMC approval.
3. Actual Possession would be withing 2 years of registration.
It means all the above things are dependent of VVMC approval which is pending for quite a long time now. And its a fact that IONIC is not able to get the approval so far for whatever the reason.
What an Investor should understand from the fact that a developer is not in a position to get the project approved.
Should it not raise a doubt in the Investor's mind. Do IONIC expects its customers to not raise any query and remain quite and calm no matter how many more years we need to wait for our dream homes.
Even after getting approval from VVMC does a customer shall trust your word of giving the possession within 2 years.
Thanks
Dear Investors
ReplyDeletePlease check link given below to share join the whats app Group of IONIC ECOCITY INVESTORS, for latest update and info
http://ionicecocitywhatsappgroup.blogspot.in/
I wish the Builder publishes photographs of the work done at regular interval... in fact if they put the camera on the site and IP address is given to the flat-buyers they can view the progress of the project online....
ReplyDeleteDear All
ReplyDeleteI have visited the site on this Sunday.
The latest updates as informed by Site officials :
1. Piling for three buildings completed.
2. Plinth to start for the same.
3. Mr. Wasim Informed the VVMC approvals received.
Planning to Visit the Andheri Office on Saturday to check the VVMC approval.
Need more people to visit there.
Get back and confirm your timings for Saturday.
This comment has been removed by the author.
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteDear All
ReplyDeleteI had called up at Andheri Office for appointment.
Initially a time was given to us on Saturday 3 P.m. but later it was not confirmed by IONIC officials hence the meeting got cancelled.
The IONIC official at Andheri office has promised to talk to the boss about meeting and he will call back me with confirmed timing as per our last discussion on Saturday afternoon.
I m awaiting his call back with confirmed appointment for meeting.
Meanwhile they had informed that there is no written VVMC approval yet. And that they have the verbal approvals on which the work is going on.
The final approval shall receive shortly as they are saying from time to time when inquired.
Best of Luck
Hope I receive a call to confirm the appointment else we need to check other ways to find out the status of VVMC approvals.
Dear Friends
ReplyDeleteI received a call from Ionic officials for confirmation about meeting. The meeting is scheduled on Thursday 18th at 3.00 pm at Ionic Andheri Office.
Who ever wants to visit can come with their allotment letter.
Also confirm your availability on our whats app group.
hi sachin,
Deletethanks for your pro activeness.
what was the update on this meeting on april 18? please do reply.
- v
The meeting briefs are
ReplyDelete1. NOC received.
2. Development agreement not registered.
3. Plot Survey No. 111(Pt)
4. CIDCO old approval was there for 13 buildings.
5. Revised Plan was submitted to VVMC on May 2012.
6. Expected VVMC approval within 3 months.
7. Currently work going on verbal approvals (as informed).
8. Nothing seems major in terms of papers yet.
9. Check whether the transfer option open for those who don't want to wait any longer.
10. Those who trust and want to stay invested can wait and be patient.
Furhter plan of action can be decided after 3 months when the VVMC approval is received as expected and informed by IONIC officials.
ReplyDeleteLets be positive and be in touch for updates.
thank you, sachin, very good and kind of you to do this :)
ReplyDeletehi Ionic,team please let us know any update on the work progress or any information please share with us.
ReplyDeleteThanks
Jonas
my post area getting deleted, but i keep on informing about the project that please dont invest hard earning money into this project,& dont fall into trap,just call police station & get him arrested.
ReplyDeletepl.send me the latest update of my ionic project on my mail id.pravinsharma838@gmail.com i have already booked flat in ionic ecocity project virar west
ReplyDeleteDear Ionic Team.
ReplyDeleteYou people are making fool to all investors but dont think that all are same and don't our patience.
Tell us exact picture on project status and pls talk logically.
Regards,
Amir
What is the current status??
ReplyDeleteWhat is actually happening?
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteDear Ionic Team,
ReplyDeleteI HAD BOOKED A FLAT IN 2010.
U HAD PROMISED US THE WORK WOULD BE COMPLETED TILL 2012.
BUT ITS 2014 ATLAST 4 YEARS PASSED NOW ..THEN EVEN IN BETWEEN YOU GAVE US AN ALLOTMENT LETTER THAT APPROXIMATELY 3 BUILDINGS IN THE YEAR OF 2014 WILL BE COMPETED.
BUT NOW EVEN 2014 IS ALSO COME TO END.. MY FLAT IS IN 3rd BUILDING I STILL DIDN'T GOT ANY PROGRESS...WE ARE STILL WAITING FOR YOUR RESPONSE..PLEASE SEND ME YOUR CURRENT STATUS.. HERE WE ARE WAITING FOR OUR DREAM HOUSE.. PLEASE REPLY AS EARLY AS POSSIBLE..