The management has seen the Blogs put up by various persons, most of these blogs seems to have been posted with total misunderstanding of the project.
We request our esteemed customers not to panic. The final plan with liberty to amend is ready to be submitted as per the directions and in compliance with all the formalities of VVMC.
The piling work is almost completed on some part of the property. We have genuine reason for delay in taking the work forward. As you all know that VVMC has been recently constituted in this area. They have not adopted DC rules as yet. They have also do not have adequate staff in their building proposal department.
They still depend on staff of CIDCO for planning of Township and large layouts. The earlier amended plan was submitted by us to VVMC on 24/05/2012. VVMC replied on 20/06/2012 which was received by us on 23/10/2012 asking for certain documents which were not in their records from the old CIDCO files.
Management has submitted the required documents and will be submitting the provisional plans before 22nd December 2012.
We would like to inform our esteemed customers that certain temporary staff members failed to communicate with our customers on a regular basis.
The management has now replaced the staff, so that all progress will now be informed through our website from time to time.
Ek aur naya Promise
ReplyDeleteJo bi hai atleast aise hi humko update toh karte raho...Your website pe bahot din se registration kiya hai buy still ur moderator has not given access to post in that..Kindly check on dat too..
ReplyDeleteFirst i need to know what is the website where u ppl will put regular update of the project.?
ReplyDeleteAnd please clear in simple language what is the progress of the project??
And as of now how much time it will take for the completion of the project.?
Hey Guys any updates please share
ReplyDeleteWhere is your provisional plan which u ppl are to be submitted before 22nd dec??
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteHow can you people can be so unconsistant and irresponsible on ur words if you fail to make ur words den atleast apologize for it rather being mute.
ReplyDeletedear ionic is there any progressive news on new year plse share tbe detail we investors are awiating for good
ReplyDeleteI have heard through some people that from 1st Jan the work has started in full swing..Pls confirm if sum1 from Virar area has seen the site recently.
ReplyDeleteAlso heard that by 1st week of Feb our Registration will be done & that there will be 16 Buildings of 14 floors instead of 36 buildings of 7 floors.
if some1 has visited the site recently please update the recent status.
I also heard that the Ionic people will call investors for registration in Feb Ist week. Also 5 machines have come to the site. Please clear if anybody has an update of the site.
ReplyDeleteThe news seems to be true Tushar. As per my info the registration will start in March 2013. And the New layout plan should come for 14 buildings before that.
ReplyDeleteI have heard the they increase the rate now 3800 psf , please update the all proper update
ReplyDeleteI hope if you progress the work in full speed then till 2015 we can get the our dream home
ReplyDeleteYes prices has been revised to 3800/sqft. Thats a confirm news
ReplyDeleteI request all the investors as work has been started in full swing so now stop worrying and start arrangment of money for registration and next instalment.
ReplyDeleteAnd please update your latest contact details with your respective broker as they will be calling you shortly for latest updates.
I know investors you have kept ao much patience, and it is commendable also, now its time to take rewards.
If anyone wants latest price list he can contact me i will send u the copy.
sohirealty@gmail.com
sohi ji, please mail me the latest price details also.
Deletejindalsre@gmail.com
Hi Shobit , Please mail me the latest price details also. at
Deletesushant.chafe@gmail.com
wow its really good news for us
ReplyDeleteHello Sohi can you please share the latest price copy on my email
digambar.designer@gmail.com
Hello Sohi can you please share the latest price copy on my email
ReplyDeleteashok.karnam87@gmail.com
i had visited the site on 12/01/13 work is started but in a slow mode, only piling for 1 building has been completed.
ReplyDeleteHi Ashokji, pls upload photos if you got form site
DeleteHi Sushant i had not clicked any pics, if next time i visit i will definately bring the pics
DeleteThis comment has been removed by the author.
ReplyDeleteTYPE
ReplyDelete1 BHK
2BHK
BUILT-UP-AREA
520 sq.ft
760 sq.ft
365 sq.ft
530 sq.ft
RATE (Per Sq.Ft.)
Rs.3800/-
Rs.3800/-
COST OF FLAT
Rs.19,76,000/-
Rs. 28,88,000/-
STAMP DUTY
As Applicable
As Applicable
REGISTRATION
As Applicable
As Applicable
SERVICE TAX
As Applicable
As Applicable
VAT
As Applicable
As Applicable
Hi Digs, Pls let know What is the source of this price list?
Deletehello Sushant you means the HTML source?
DeleteI get the document from the Sobhit, you can share the emamil with him .
on 13th Jan I visited at site. Mr. Pant from site told one big piling machine arrived at site and stand near Olanda Naka & Its true. else the progress at site as it is as previous. thanks.
ReplyDeletedear every one i had also booked 1bhk and i had also visited the site on sunday 13th jan2013.it is true that the machine was standing at side on traller beside road. i also talk to the person attending the visitors to show sample flat he say it will take 3months to do registration pilling work is in progress .to do work fast machine is there which will cover time . there is also. no any news about 16 building plan. he told there is 36 bldg in 1st phase and till we don't have any official report for new plan.but he told till june 2015 we will get the possession.
ReplyDeleteHi everyone once you visit the site next time please try to shoot the photo
ReplyDeleteCurrent rate is 3000 PSF, as stated by builder. I have 2BHK flat with me , I would like to sell it on 2800 PSF. I had booked on 2700 PSF one year ago. If anyone interested then please let me know.
ReplyDeleteSOrry current rate is 3800 PSF, as per builder. I would like to sell it on 2800 PSF.
ReplyDeleteAny body has visited to Builder office for verification of new layout plan. Pls inform me the changes and have copy then please mail me at mahendra79in@gmail.com. And site photo if available then pls mail me.
ReplyDeleteWhen we get written letter from builder then we trust on news regarding registration of property. Main is work to be start on fast basis then it is possible.
I have a 01 BHK Flat Booked.
ReplyDeleteCurrent rate is 3800/- PSF.
I am ready to sell it Urgently @ 3000/- PSF.
Contact me if any one is interested.
Ramesh.C : 9619268666.